2023
Week of Jan. 23: Work will begin this week to trench and install the reservoir liner.
Week of Jan. 16: Under-tank construction is continuing this week.
Week of Jan. 2: Pipe work will continue this week, followed by the installation of encasements to protect the piping.
2022
Week of Dec. 26: Work will be continuing this week on undertank piping.
Week of Dec. 19: On-site construction will continue this week. No work will take place on Dec. 23. 26 and 30.
Week of Dec. 12: The installation of under-tank piping will continue as weather permits, with pipe encasements beginning next week.
Week of Dec. 5: Work will begin this week to install under-tank piping.
Week of Nov. 21: The access road to the site is being demolished this week, and grading and potholing will also continue.
Week of Nov. 14: Interim grading will be done to prepare the site for construction.
Week of Nov. 7: Potholing work will be starting to identify underground utilities. That work is expected to be completed in mid-November.
Week of Oct. 24: Demolition work is being done as a part of the project. There will be no impact on services, which will continue to be provided throughout the duration of the project.
Week of Oct. 10: Construction began this week with the setup of equipment and temporary facilities, and the installation of a construction fence.